MOUNT PLEASANT PHASE TWO

Revitalising business critical assets

LONDON, ENGLAND

MOUNT PLEASANT PHASE TWO

This involved the refurbishing of business critical assets, which meant consolidating Royal Mail's delivery office in London.

The delivery office and administration building were refurbished, including two floors for new canteen facilities and offices, a CAT B fit out across over four floors, full window replacement and façade, and redesign of distribution facilities.
RLB employed the design team and consultants and managed the project from initial design through to completion and occupation.
The construction cost for the project was about £53 million, within a London consolidation project with a development budget of £60 million.
At the start of the project, consultation was undertaken with numerous stakeholders who had clearly defined objectives for the new facility.
Despite the ever-changing design criteria, project management, design and quantity surveying teams worked together to deliver a complex project to meet the client’s needs.
This was achieved over a phased two year program while the building remained fully operational.

At a glance

  • Client
    Royal Mail Group Property
  • Services
    Project & Programme Success, Commercial Success, Specialist Solutions, Building Surveying, Project Management, Cost Planning & Value Management
  • sector
    Offices
  • Location
    London, United Kingdom

Related and Notable Projects...

  • Re-thinking and enhancing existing spaces

    123 VICTORIA STREET
  • Offering world-class business infrastructure and facilities

    ABU DHABI AIRPORT FREE ZONE
  • Maximizing budgets for office-fit out projects

    ROYAL BANK OF CANADA DATA CENTRE AND…