Data centre projects can’t run on hindsight

  • Insights
  • Data centre projects can’t run on hindsight
About this article
Terence Tracey

Author

Terence Tracey

Themes

Perspective , Perspective 2026
Market Insights

Sign Up for Market Trends & Insights

Connect

Data centre schedules are too often used to explain what has already happened. Their real value lies in testing what could happen next.

50–70% of hyperscale and colocation data centre programs can be driven by long-lead mechanical, electrical and plumbing equipment.

As the AI race continues to accelerate, hyperscale data centre construction has become as much a question of timing as it is of technology.

A facility doesn’t generate revenue until it is operational. Schedule-driven delays can translate into millions of dollars per month in deferred revenue, while competitors with active facilities gain market share.

Yet, one of the most valuable tools on any construction project is often underused: the schedule.

Too often, construction schedules are treated as a static reporting document rather than a strategic tool. Schedule updates tend to focus on what has already occurred, not on modelling future scenarios or balancing tradeoffs.

In the best-case scenario, projects managed this way can still progress smoothly. The contractor provides regular progress reports, risks fail to materialise, and the data centre reaches commissioning on time and within budget. But this is not always the case. Even when projects do stay on track, traditional scheduling offers less insight into why, making successful outcomes more difficult to replicate.

Alternatively, reactive scheduling can contribute to cascading delays and significant cost exposure. Misaligned permitting sequences, procurement blind spots around long-lead electrical equipment, or competition for labour in constrained markets can quickly compound. Without a schedule that actively integrates all of these timelines, risks are often identified too late.

The solution is to position the schedule as a forward-looking tool for decision-making rather than a retrospective record of events.

Long-lead equipment and utility constraints can be modelled directly into the project schedule to determine when critical components must arrive. Teams can test “what-if” scenarios: Should a long-lead item be expedited? Could work be resequenced? Could an alternate vendor be engaged?

Modelling scenarios early can guide constructibility decisions. For example, teams can test whether a tilt-up exterior panel system or traditional steel and façade erection offers the best path to delivery.

This proactive approach reveals true procurement float and supports informed business decisions before construction is underway, not after crews are already mobilised.

The hyperscale data centre construction market is high stakes and even higher complexity. Owners can no longer afford to view schedules as static reporting deliverables. With smarter, dynamic scheduling from the earliest stages, speed-to-market becomes more predictable, outcomes become more measurable, and with that data, success becomes replicable.

Success depends on delivering with certainty

Europe’s data centres sector is preparing for unprecedented expansion, reveals RLB’s Data Centre Trends Report 2026.

Data centre operators expect to commission 67MW of capacity, on average, in 2026. This represents a 42% year-on-year increase and a staggering 319% increase since 2023.

The report, based on a survey of 700 senior executives, highlights that the sector’s ability to convert growing demand into delivered capacity is under mounting pressure due to power grid constraints, permitting delays and specialist labour shortages. An added technical challenge is that the AI boom is driving up power density and cooling requirements.

In the foreword, Service Transformation Director Andrew Fettes-Brown writes: “As projects grow in scale and complexity, success will depend on industrialising delivery, strengthening collaboration, and treating energy and supply chains as strategic priorities. The advantage belongs to those who can deliver with certainty.”

Read the full report for our expert recommendations on scaling the next wave of digital infrastructure at: Data Centres – Data Centre Trends Report 2026

Data centres 2026

Fast facts

35%

Cite access to power as one of the top three barriers to expanding data centre capacity.

29%

Point to the price and lead time of materials and equipment as a major barrier to growth.

39%

Say construction skills are among the hardest to access across the data centre development lifecycle.

4.3%

Expected price increase for battery energy storage systems in 2026, ahead of copper cable at 4.0% and cooling systems at 3.7%.

FURTHER INFORMATION:

Terence Tracey
Terence Tracey

Vice President | Head of Growth & Strategy